Terms and conditions
PLAN-B NET ZERO stands for a future without fossil fuels!
General terms and conditions
for the supply of electricity to household customers
As of: 05/2026
1. Who is the Contracting Party?
PLAN-B NET ZERO ENERGY GmbH (here inafter referred to as "PLAN-B NET ZERO ENERGY")
Registered Office: Mühlheimer Tor – Dieselstr. 2, 63165 Mühlheim am Main Managing Director: Markus Schunk
Registry Court: Amtsgericht Charlottenburg, HRB 151699 B
VAT Identification Number according to §27a
VAT ID: DE 293086561
2.What kind of electricity does PLAN-B NET ZERO ENERGY supply?
The electricity supplied by PLAN-B NET ZERO ENERGY is 100% green electricity. The grid operator is solely responsible for the quality of the electricity, particularly the nominal voltage and nominal frequency.
3.Who can enter into a contract with PLAN-B NET ZERO ENERGY?
3.1. In principle, any private individual and any company that primarily consumes electricity for their own use can enter into a contract with PLAN-B NET ZERO ENERGY. Supply is provided outside of the basic supply.
3.2. No maintenance services are offered.
3.3. Electricity is supplied exclusively to household and commercial customers for their own consumption, up to an annual requirement of 100,000 kWh/year according to a standard load profile and/or a maximum capacity of 30 kW.
3.4. If the actual supply quantity exceeds the maximum annual supply quantity or the maximum capacity, PLAN-B NET ZERO ENERGY reserves the right to terminate the supply contract with two weeks' notice to the end of a calendar month.
3.5. PLAN-B NET ZERO ENERGY has no obligation to supply if the grid operator does not permit supply according to the standard load profile, no supplier framework agreement exists for the grid area, no legally valid grid connection and connection usage contract exists for the supply point, or the grid connection is interrupted, or the supply is rejected by the grid operator for other reasons.
4.How and with whom is a contract concluded? How is communication regarding the contract handled with PLAN-B NET ZERO ENERGY?
4.1 The customer's contractual partner is PLAN-B NET ZERO ENERGY GmbH. The conclusion of the contract can be initiated by the customer, among other ways, online via the PLAN-B NET ZERO ENERGY website (planbnetzero-energy.com – hereinafter referred to as "website").
4.2. PLAN-B NET ZERO ENERGY concludes the contracts required for the supply with grid operators. These include, among other things, the operation of metering points by the grid operator as the responsible metering point operator, provided that the customer has not concluded a separate contract with another metering point operator in this regard.
4.3. Offers for electricity tariffs created by PLAN-B NET ZERO ENERGY based on customer information do not constitute a legally binding offer to the customer.
4.4. Only by signing the order form or, online, by clicking the "Order with obligation to pay" button, does the customer submit a binding offer to PLAN-B NET ZERO ENERGY to conclude a contract (hereinafter referred to as "order"). Until the binding submission of the order, the customer can correct their selection online at any time by using the correction aids provided in the ordering process.
4.5. If the customer indicates "supplier change" as the reason for their order during the ordering process, they remain bound by their order for the duration of the supplier change process. In this case, the contract will be concluded taking into account the date on which the previous supplier accepts the termination of the previous supplier for the supply point (if applicable) and on which the respective local grid operator confirms the start of grid usage.
4.6. PLAN-B NET ZERO ENERGY will handle the termination with the previous supplier on behalf of the customer. However, if the customer has a special right of termination with the previous supplier, the customer must terminate their contract with the previous supplier themselves.
4.7. PLAN-B NET ZERO ENERGY may check the creditworthiness of a new customer. This is done in compliance with data protection laws via its external service provider. PLAN-B NET ZERO ENERGY is entitled to refuse the acceptance of an order if the creditworthiness is insufficient.
4.8. The contract is concluded as soon as the order has been confirmed by PLAN-B NET ZERO ENERGY. The order confirmation will always be issued before PLAN-B NET ZERO ENERGY begins the contractual supply of electricity. The order confirmation will be sent in text form via email and will contain all information necessary for the conclusion of the contract, including the customer's supply point and the identification number used to designate the withdrawal point (hereinafter referred to as "meter number"). After the contract is concluded, the customer will be provided with a summary of the most important contract terms. PLAN-B NET ZERO ENERGY reserves the right to reject change requests from customers who have already been supplied by PLAN-B NET ZERO ENERGY twice within the last 12 months, each with a minimum contract term of one month. 5. 6. 7.
4.9. Unless these contract terms explicitly require communication in 'text form via email', declarations can also be made in any other text form than email (e.g., fax, letter). The email address of PLAN-B NET ZERO ENERGY is: kunde@planbnetzero-energy.com. Emails from PLAN-B NET ZERO ENERGY will be sent to the email address provided by the customer during registration. PLAN-B NET ZERO ENERGY reserves the right to send communications by post in individual cases. For smooth communication, the customer must always keep the email address stored with PLAN-B NET ZERO ENERGY up to date. Changes to the email address must be communicated to PLAN-B NET ZERO ENERGY without delay.
4.10. For contractual purposes, the customer agrees to receive all communication in electronic form, unless mandatory legal provisions require a different form of communication. Personal data such as bank code, account, and telephone numbers are only partially displayed for protection.
4.11. Data transmission over the internet (e.g., when communicating via email) may have security vulnerabilities. Complete protection of data from third-party access is not possible. When communicating via email, all documents are currently sent unencrypted.
4.12. Supply also begins on the date specified in the order confirmation. However, supply will not commence before the customer's cancellation period expires according to §§ 355 para. 2, 356 para. 2 no. 2 BGB, unless the customer explicitly requests PLAN-B NET ZERO ENERGY to do so.
5.Can a consumer cancel the contract?
The contract can be revoked within fourteen days of contract conclusion (order confirmation) without stating any reasons. For this, please refer to the cancellation policy sent with the order confirmation.
6.What happens when changing suppliers? When does electricity supply begin?
6.1. PLAN-B NET ZERO ENERGY will carry out any potential supplier change promptly and free of charge, in compliance with legal regulations and contractually agreed deadlines.
6.2. In the event of a supplier change, PLAN-B NET ZERO ENERGY is required to immediately confirm to the customer in text form whether and on what date it can commence the supply requested by the customer.
6.3. Electricity supply begins on the date specified in the order confirmation, but no earlier than when:
- zwischen PLAN-B NET ZERO ENERGY, dem örtlichen Netzbetreiber und/oder dem Vorlieferant bzw. Messstellenbetreiber des Kunden sämtliche Fragen zum Netzzugang bzw. zum Messstellenbetrieb sowie zur Übernahme des Kunden geregelt sind,
- the upstream supplier has confirmed the termination of the previous contract and
- the local grid operator has confirmed the start of grid usage.
6.4. This date depends on several conditions, such as the termination of the previous supply contract, no blocking of the connection, confirmation of grid usage by the grid operator, and the grid operator's approval of the metering concept. This process is free of charge for the customer and will be implemented as quickly as possible. PLAN-B NET ZERO ENERGY will communicate the start of supply to the customer.
6.5. Should PLAN-B NET ZERO ENERGY actually be unable to commence electricity supply on the date specified in the order confirmation, the customer will continue to be supplied either by the previous supplier or by the basic supplier due to the basic supplier's obligations under Sections 36, 38 of the EnWG.
6.6 PLAN-B NET ZERO ENERGY is not obliged to commence energy supply if the customer's connection is blocked at the scheduled start of supply or if no grid connection exists.
7. Is the customer permitted to operate their own plants?
For the duration of the contract, the customer is obliged to procure their entire electricity requirements for the supply point from PLAN-B NET ZERO ENERGY. Excluded is the coverage of demand by own combined heat and power (CHP) plants up to 50 kW electrical output and from renewable energies; furthermore, by own plants that serve exclusively to ensure electricity supply in the event of an interruption of the power supply (emergency generators).
8.How is the electricity supply remunerated?
8.1. The electricity price consists of a basic price and a consumption-based price. The amount is agreed upon at the time of contract conclusion. If an effective price change occurs thereafter in accordance with Section 10, the changed price shall replace the previously agreed price.
8.2. The customer undertakes to pay for the electricity supplied and consumed.
9.What costs are included in the electricity price?
The electricity price includes the following costs: Procurement and sales costs, including billing costs, as well as value-added tax, electricity tax, concession fees, grid charges, and the fees of the metering point operator for metering point operation, measurement, and billing, the levy according to Section 26 of the Combined Heat and Power Act [CHP Act levy], the levy according to Section 19, Paragraph 2 of the Electricity Grid Charges Ordinance [§ 19 Strom NEV levy], the levy according to Section 17f of the Energy Industry Act [Offshore Liability Levy], the levy according to Section 18 of the Ordinance on Disconnectable Loads [Levy for Disconnectable Loads – AbLaV], in their respective valid versions.
Upon the introduction of new or the elimination of existing taxes, duties, or government-induced levies and surcharges affecting the electricity price, these will be added as new price components or removed, respectively, in accordance with the actual burden or relief incurred, provided that passing them on to the end customer is permissible and insofar as these price components were not already foreseeable at the time of contract conclusion.
10. Can PLAN-B NET ZERO ENERGY change prices?
10.1. Price changes by PLAN-B NET ZERO ENERGY are made through unilateral determination of performance in the exercise of equitable discretion in accordance with Section 315 of the German Civil Code (BGB).
10.2. The customer may have the fairness of the respective price change reviewed by a civil court. In the unilateral determination of performance by PLAN-B NET ZERO ENERGY, only changes in costs relevant for price calculation according to Section 9 are to be considered. However, for tariffs with a limited price guarantee, a price change cannot be based on changes in procurement and sales costs, including billing costs, during its term. PLAN-B NET ZERO ENERGY is entitled to implement a price change in the event of cost increases and obliged to do so in the event of cost reductions. When determining prices, PLAN-B NET ZERO ENERGY is obliged to consider cost increases only by offsetting them against opposing cost reductions and to net out cost increases and cost reductions.
10.3. PLAN-B NET ZERO ENERGY must determine the scope of a price change such that cost reductions are accounted for using the same business economic standards as cost increases. In particular, PLAN-B NET ZERO ENERGY may not pass on cost reductions later than cost increases.
10.4. Price changes will only become effective on the first day of a month and only after notification in text form, with notification provided at least one month before the intended change takes effect.
10.5. If PLAN-B NET ZERO ENERGY changes prices, the customer has the right to terminate the contract without observing a notice period, effective from the date the price change comes into force (special right of termination). PLAN-B NET ZERO ENERGY will explicitly inform the customer of the upcoming change in text form via email. Termination must be in text form. PLAN-B NET ZERO ENERGY will promptly confirm the customer's termination within one week of receipt in text form via email, stating the contract end date. The right to ordinary termination remains unaffected.
10.6. Changes to value-added tax (VAT) in accordance with the Value-Added Tax Act, as well as future reductions in charges due to a decrease in the balance of calculation components according to Section 40, Paragraph 3, Number 3 of the Energy Industry Act (EnWG), may be passed on to the customer unchanged without prior notice and without the customer's right to terminate the contract without notice.
11. How is delivered electricity measured?
The electricity supplied is determined by the metering equipment in accordance with the provisions of the Metering Point Operation Act.
12. How is supplied electricity metered?
12.1. For the determination of the electricity supplied, PLAN-B NET ZERO ENERGY is entitled to use the meter readings transmitted by the local grid operator, metering point operator, or a third party responsible for metering.
12.2. For measurements using a smart metering system as per Section 2, Sentence 1, Number 7 of the Metering Point Operation Act, the values specified in Sentence 1, Number 1 shall be used preferentially. PLAN-B NET ZERO ENERGY will state in the invoice how a meter reading used by it was determined.
12.3. PLAN-B NET ZERO ENERGY may read the metering equipment itself or require the customer to read it, if this is done
- for billing purposes,
- due to a change of supplier or
- should PLAN-B NET ZERO ENERGY have a legitimate interest in verifying the reading.
12.4. The customer may object to a self-reading in individual cases if it is unreasonable for them. In the event of a justified objection, PLAN-B NET ZERO ENERGY may not charge a separate fee for its own meter reading.
12.5. For the purpose of meter reading, the customer must grant access to their property and premises to the authorized representative of the grid operator, metering point operator, or PLAN-B NET ZERO ENERGY, provided they carry identification. The customer must be notified of this in advance, either by direct communication or by a notice posted in the respective building. The notification must be given at least one week before the scheduled access date; at least one alternative date must be offered. The customer must ensure that the metering equipment is accessible.
12.6. If the local grid operator or PLAN-B NET ZERO ENERGY cannot access the customer's property and premises for meter reading purposes, PLAN-B NET ZERO ENERGY may estimate consumption based on the last reading or, for a new customer, based on the consumption of comparable customers, with due consideration of the actual circumstances. The same applies if the customer fails to perform an agreed self-reading or performs it late.
13.How are electricity & bonus billed?
13.1. PLAN-B NET ZERO ENERGY usually bills the supplied electricity once a year after the supplied electricity has been read or determined. However, the billing period must not significantly exceed 12 months. The customer will receive the invoice no later than 6 weeks after the end of the billing period. After termination of the supply relationship, the customer will receive the final invoice no later than 6 weeks later.
13.2. Instead of annual billing in the customer portal, the customer may request monthly, quarterly, or semi-annual billing. In the case of desired interim billing, the customer undertakes to read the required meter readings themselves and to submit them unsolicited in text form via email to PLAN-B NET ZERO ENERGY by the billing dates communicated by them. If the meter readings are not submitted on time, PLAN-B NET ZERO ENERGY is entitled to estimate the values required for billing.
13.3. PLAN-B NET ZERO ENERGY may demand advance payments for the electricity supplied during the billing period. The amount of the advance payments is calculated proportionally for the period of the advance payment according to the consumption in the last billing period. If such a calculation is not possible, the advance payment will be based on the average consumption of comparable customers. If the customer credibly demonstrates that their consumption is significantly lower, PLAN-B NET ZERO ENERGY will take this into appropriate consideration.
13.4. The customer agrees to the electronic transmission of invoices, billing information, and the final invoice by PLAN-B NET ZERO ENERGY. Billing information is based on the determined consumption.
13.5. Upon request, the customer will receive the invoices and billing information free of charge in paper form once a year. Supplementary information on consumption history since the start of the contract will be provided upon the customer's request, if available.
13.6. If the billing results in a credit for the customer, PLAN-B NET ZERO ENERGY will refund this within 2 weeks or offset it against the next advance payment.
13.7. If prices change within a billing period, the consumption relevant to the new prices will be calculated proportionally. Seasonal consumption fluctuations will be appropriately taken into account based on empirical values for comparable customers. The same applies to changes in the VAT rate and other cost components as per Section 9. Advance payments may also be adjusted in such cases.
13.8. PLAN-B NET ZERO ENERGY may grant the customer a bonus as part of certain tariffs or limited-time promotions. A bonus is not part of the agreed electricity price and does not constitute consideration for the electricity supply, but rather a voluntary additional benefit in accordance with these General Terms and Conditions.
13.9. If the customer has been promised a percentage bonus or a fixed bonus amount in euros that does not fall under the following paragraphs, this will be granted after the end of the first supply year. The bonus is granted as a credit within the annual consumption statement and is offset against the total costs of the actual electricity consumption in favor of the customer.
13.10. If a so-called "immediate bonus" has been agreed upon, it becomes due and is paid to the customer at the contractually agreed time, up to the promised amount, provided that the contractual relationship remains uncancelled at that time.
13.11. If a "first-year discount" or an "advance payment bonus" has been agreed upon, the customer receives a percentage discount, up to the agreed amount, on the total costs of the actual electricity consumption within the first supply year. PLAN-B NET ZERO ENERGY is entitled to reduce the monthly advance payments during the first supply year by the corresponding percentage. The final calculation and offsetting will be carried out as part of the annual consumption statement based on actual consumption.
13.12. There is no entitlement to a new customer bonus if
- the contractual relationship is terminated by the customer before the expiry of a supply year or for reasons attributable to the customer, or
- the customer was already supplied by PLAN-B NET ZERO ENERGY at the same supply point within the last six months prior to re-engagement.
13.13. There is no entitlement to the payment of an immediate bonus if the contractual relationship is terminated by the customer or for reasons attributable to the customer before the agreed payment date, or if the customer has already been supplied by PLAN-B NET ZERO ENERGY at the same consumption point within the last six months prior to renewed commissioning.
13.14. First-year discounts or advance payment bonuses already granted must be repaid if the conditions for their granting subsequently cease to apply.
13.15. Offsetting a bonus against claims by PLAN-B NET ZERO ENERGY arising from advance payments or invoices is excluded before the first annual consumption statement is issued, unless these General Terms and Conditions provide otherwise.
14.When are invoices and advance payments due?
14.1. Invoices and advance payments are due at the time specified by PLAN-B NET ZERO ENERGY, but no earlier than 2 weeks after receipt of the payment request.
14.2. The customer may only offset claims by PLAN-B NET ZERO ENERGY with undisputed or legally established counterclaims.
15.How can the customer pay?
15.1. The customer can choose between payment by issuing a SEPA Core Direct Debit mandate and a bank transfer to a PLAN-B NET ZERO ENERGY bank account, which incurs a fee for the customer.
15.2. Should the customer's account or bank account lack sufficient funds, incorrect bank details be provided, and PLAN-B NET ZERO ENERGY be unable to collect the due installment, or if the customer fails to transfer a due installment on time, PLAN-B NET ZERO ENERGY is entitled to charge the customer a fee ("chargeback fee") to cover the actual costs incurred for a chargeback or payment tracking. The chargeback fee is independent of the amount of the claim.
16.What applies in case of payment default?
16.1. If the customer defaults by not fully making payments equivalent to one monthly installment within two months, or by not making payments equivalent to two or more monthly installments on time, PLAN-B NET ZERO ENERGY may, if PLAN-B NET ZERO ENERGY again requests payment or has the amount collected by an authorized agent, charge a flat fee for the resulting costs in structurally comparable cases; the flat fee calculation must be easily verifiable. The flat fee may not exceed the costs typically expected in the ordinary course of business. Upon the customer's request, the basis for the calculation must be provided.
16.2. Repeated payment delays, despite receiving a warning letter from PLAN-B NET ZERO ENERGY announcing immediate termination to the customer two weeks in advance, constitute a material breach of contract and entitle PLAN-B NET ZERO ENERGY to terminate the contract without notice.
16.3. Furthermore, PLAN-B NET ZERO ENERGY is entitled to interrupt the supply in accordance with clause 20.
17.What applies in case of calculation errors?
17.1. If an inspection of the metering devices reveals an exceedance of the permissible error limits or if errors are found in the calculation of the invoice amount, PLAN-B NET ZERO ENERGY must refund any overpayment or the customer must pay the deficit. If the extent of the error cannot be clearly determined or if a metering device does not display it, PLAN-B NET ZERO ENERGY will estimate the consumption for the period since the last error-free reading based on the average consumption of the preceding and subsequent billing periods to the error detection, or based on the previous year's consumption; the actual circumstances must be appropriately considered. In the event of calculation errors due to a malfunctioning metering device, the corrected consumption determined by the metering point operator and communicated to the customer shall form the basis for recalculation.
17.2. Claims under clause 17.1 are limited to the billing period preceding the detection of the error, unless the effect of the error can be determined over a longer period; in this case, the claim is limited to a maximum of three years. The three-year period is calculated retrospectively from the point in time when the customer became aware of the possibility of an additional charge. In the case of a refund, the relevant point in time is when PLAN-B NET ZERO ENERGY became aware of the possibility of a refund.
18. What happens in case of a disruption?
18.1. If an interruption or irregularity in the electricity supply occurs due to a disruption of grid operation, including the grid connection, the customer may be entitled to claims against the customer's grid operator in accordance with statutory provisions. PLAN-B NET ZERO ENERGY is exempt from the obligation to perform if an interruption or irregularity in electricity supply is a consequence of a disruption of grid operation, including the grid connection. Claims due to a disruption of grid operation, including the grid connection, can only be asserted against the grid operator.
18.2. PLAN-B NET ZERO ENERGY undertakes, at the customer's request, to inform the customer of the reasons for an interruption or irregularity caused by the grid operator, provided these are known to PLAN-B NET ZERO ENERGY or can be reasonably clarified.
18.3. For claims not covered by Section 18.1, the liability of PLAN-B NET ZERO ENERGY and its agents and/or vicarious agents for damages caused by fault is limited to intentional acts and gross negligence. This does not apply to damages resulting from injury to life, limb, or health, or from the culpable breach of material contractual obligations (cardinal obligations). In the event of a breach of material contractual obligations not caused by intentional or grossly negligent conduct, PLAN-B NET ZERO ENERGY’s liability is limited to the damage that the liable party foresaw as a possible consequence of the breach at the time the respective contract was concluded, or should have foreseen given the circumstances of which it was aware or should have been aware. The provisions of the Product Liability Act and the Liability Act remain unaffected.
19. When is PLAN-B NET ZERO ENERGY exempt from the obligation to supply?
19.1. PLAN-B NET ZERO ENERGY is not obliged to commence energy supply if the customer's connection is blocked at the intended start of supply or if no grid connection exists. In the following cases, PLAN-B NET ZERO ENERGY is also exempt from the obligation to supply:
19.2. insofar and as long as the grid connection or grid and connection usage has been interrupted by the grid operator according to § 17 or § 24 paras. 1, 2 and 5 of the Low Voltage Connection Ordinance / Low Pressure Connection Ordinance or
19.3. insofar and as long as the grid connection or grid usage and/or connection usage has been interrupted by the grid operator for other reasons for which PLAN-B NET ZERO ENERGY is not responsible. The same applies if this involves consequences of a disruption to metering point operation or
1
19.4. insofar and as long as PLAN-B NET ZERO ENERGY is prevented from procuring or contractually supplying electricity for the following reasons:
- 19.4.1. Force Majeure: Force Majeure, within the meaning of these terms, refers to any external event, unrelated to business operations, that is unforeseeable and unavoidable even with the utmost reasonably expected care (e.g., severe weather), or
- 19.4.2. Other circumstances that PLAN-B NET ZERO ENERGY cannot eliminate or whose elimination cannot be economically expected of it in accordance with Section 36, Paragraph 1, Sentence 4 of the EnWG.
- 19.4.3. The continuation of the contract is unreasonable if the changes in circumstances lead to an unjustified shift in the originally agreed balance of performance and consideration, which is inconsistent with the purpose of the contract and the intent of the parties at the time of contract formation.
- 19.4.4. In cases of economic unviability (e.g., if the usage-based price does not cover the costs for grid fees, taxes, levies, and charges), PLAN-B NET ZERO ENERGY may refuse delivery or terminate the contract.
20. When is PLAN-B NET ZERO ENERGY entitled to interrupt the supply?
20.1. PLAN-B NET ZERO ENERGY is entitled to cause the customer's supply to be interrupted without prior notice from the grid operator if the customer is culpably in material breach of a contractual provision and the interruption is necessary to prevent the use of energy by circumventing, tampering with, or prior to the installation of metering equipment.20.1. PLAN-B NET ZERO ENERGY is entitled to have the customer's supply interrupted by the grid operator without prior warning if the customer culpably breaches a contractual provision to a not insignificant extent and the interruption is necessary to prevent the use of energy by circumventing, influencing, or prior to the installation of metering devices.
20.1. PLAN-B NET ZERO ENERGY is entitled to have the customer's supply interrupted by the grid operator without prior warning if the customer culpably breaches a contractual provision to a not insignificant extent and the interruption is necessary to prevent the use of energy by circumventing, influencing, or prior to the installation of metering devices.
20.2. PLAN-B NET ZERO ENERGY may, in conjunction with the demand for payment, threaten to suspend supply, provided that this is not disproportionate to the severity of the violation.
20.2. PLAN-B NET ZERO ENERGY may, at the same time as issuing a reminder, threaten to interrupt the supply, provided this is not disproportionate to the severity of the breach.
20.3. Along with the notice, PLAN-B NET ZERO ENERGY also informs the customer of options for avoiding the service interruption that do not incur additional costs.
20.3. With the threat of interruption, PLAN-B NET ZERO ENERGY will also inform the customer about options to avoid the supply interruption that do not incur additional costs.
20.4. The customer will be notified of the start of the supply interruption at least one week in advance.20.4. The customer will be notified of the start of the supply interruption at least one week in advance.
20.4. The customer will be notified of the start of the supply interruption at least one week in advance.
20.5. Suspension of service due to late payment is possible under the conditions set forth above only if the customer is in default on payment obligations amounting to twice the amount of the installment or advance payment due for the current calendar month, or, in the event that no installments or advance payments are due, at least one-sixth of the estimated amount of the annual bill. In this case, the payment arrears must amount to at least 100 euros. When calculating the amount by which the customer is in arrears, the following applies:
20.5. An interruption due to payment default is only possible under the aforementioned conditions if the customer is in default of payment obligations amounting to twice the pro-rata advance or prepayment for the current calendar month, or, if no advance or prepayments are due, with at least one-sixth of the estimated annual bill amount. The payment default must be at least 100 Euros. When calculating the amount by which the customer is in default, the following applies:
- Any down payments will be deducted.
- Unadjudicated claims that the customer has formally, timely, and conclusively disputed will not be taken into account.
- Arrears that are not yet due because of an agreement between the contracting parties will not be taken into account.
- Arrears resulting from a disputed price increase that has not yet been legally decided will not be taken into account.
20.6. PLAN-B NET ZERO ENERGY will arrange for the supply to be restored immediately once the reasons for the interruption have ceased and the customer has reimbursed the costs of the interruption and restoration of supply. The costs can be calculated as a flat rate for structurally comparable cases. The flat rates will not exceed the costs to be expected in the ordinary course of events. The customer is free to prove that PLAN-B NET ZERO ENERGY incurred no damage or significantly less damage. Upon the customer's request, PLAN-B NET ZERO ENERGY will provide proof of the basis for calculation.
21. How long does the contract run and how can it be terminated?
21.1. The contract runs for an indefinite period and can be terminated by the customer or PLAN-B NET ZERO ENERGY at any time with one month's notice in text form ("ordinary termination"). The notice period begins upon receipt of the termination by the respective contracting party.
21.2. For tariffs with a fixed contract term, the customer unilaterally has the right to switch to a tariff without a fixed contract term within the agreed contract period. In this case, the customer must notify the change in text form, specifying the newly chosen tariff, with one month's notice before the change date. PLAN-B NET ZERO ENERGY will confirm the customer's change immediately by email within one week of receiving the notification. The confirmation of the change will include a summary of the key contract terms for the chosen tariff without a fixed contract term.
21.3. If the customer wishes to terminate because they have chosen another supplier, they can authorize that supplier to handle the termination. If the customer wishes to terminate the contract with PLAN-B NET ZERO ENERGY without having chosen a new supplier, the termination of the contract with PLAN-B NET ZERO ENERGY must be in text form.
21.4. Any termination must always be in text form. Sending a written termination by post is not necessary, but is, of course, possible.
21.5. PLAN-B NET ZERO ENERGY will confirm a customer's termination, specifying the contract end date, immediately by email within one week of receiving the termination.
21.6. The right to extraordinary termination for good cause in accordance with § 314 BGB remains unaffected. Good cause exists, in particular, in the event of a repeated, non-insignificant breach of essential contractual obligations despite a warning (e.g., in case of payment default).
21.7. In the event of an extraordinary termination by the customer, it is advisable, based on experience, for faster processing of the supplier change, to terminate the contract oneself and to inform the new supplier that it is an extraordinary termination by the customer.
22.What happens if the customer changes residence?
22.1. In the event of a change of residence, the customer undertakes to inform PLAN-B NET ZERO ENERGY in text form, no later than six weeks before moving out, of the move-out date, the new delivery address, the new billing address, the move-in date, and, if known, the new meter number.
22.2. Together with the notification, but no later than six weeks before moving out, the customer may terminate the contract for supply at the previous consumption point without notice, effective on the communicated move-out date or at a later date.
22.3. In the event of a change of residence by the customer, PLAN-B NET ZERO ENERGY will check whether supply at the new consumption point is possible and whether it can offer the customer supply at the new residence under the previous contract terms. Otherwise, PLAN-B NET ZERO ENERGY will check for a possible supply at the new consumption point at new prices, including a new limited price guarantee. PLAN-B NET ZERO ENERGY will communicate the result of this check to the customer within 2 weeks.
22.4. The customer's extraordinary termination will not become effective if PLAN-B NET ZERO ENERGY informs the customer within 2 weeks of receiving the extraordinary termination that supply at the new consumption point is possible under the previous contract terms.
22.5. If the customer does not accept PLAN-B NET ZERO ENERGY's offer for a possible supply at new prices, including a new limited price guarantee, within 2 weeks, the contract will end on the move-out date communicated by the customer, unless the customer has terminated the supply at the previous consumption point with effect from a later date.
22.6. Should the customer inform PLAN-B NET ZERO ENERGY too late or not at all about the change of residence, the customer is responsible for any damage arising therefrom and is obliged to compensate PLAN-B NET ZERO ENERGY for it.
23.Can these Terms and Conditions change?
23.1. In the event that PLAN-B NET ZERO ENERGY wishes to amend these GTC, the amended GTC will be offered to the customer in text form via email at least 6 weeks before the date on which the new GTC are intended to become effective.
23.2. The amendments offered by PLAN-B NET ZERO ENERGY shall only become effective if the customer accepts them, if applicable, by way of the fictitious consent regulated below in Section 23.3.
- 23.2.1. If a not insignificant disruption to the balance of the contractual relationship existing at the time of contract conclusion must be remedied due to unforeseeable changes that PLAN-B NET ZERO ENERGY did not cause and over which PLAN-B NET ZERO ENERGY has no influence.
23.3. The customer's silence shall only be deemed acceptance of the amendment offer (fictitious consent) if
- 23.3.1. the amendment offer from PLAN-B NET ZERO ENERGY is made to ensure the conformity of the contractual provisions with a changed legal situation
to restore, because a provision of these GTC
- no longer complies with the legal situation due to a change in laws, including directly applicable legal provisions of the European Union, or
- becomes invalid or may no longer be used due to a legally binding court decision, even by a court of first instance, or
- due to a binding order from a national (e.g., Federal Network Agency) or international (e.g., European Commission) authority responsible for PLAN-B NET ZERO ENERGY, it can no longer be reconciled with PLAN-B NET ZERO ENERGY's legal obligations, and
- 23.3.2. the customer has not rejected the amendment offer from PLAN-B NET ZERO ENERGY before the proposed effective date of the respective amendment. PLAN-B NET ZERO ENERGY will inform the customer in the amendment offer about the consequences of their silence.
23.4. The fiction of consent does not apply
- for changes to the main contractual obligations, including price changes, or
- for changes that are equivalent to concluding a new contract, or
- for changes that significantly alter the previously agreed balance of performance and consideration,
would significantly shift in favor of PLAN-B NET ZERO ENERGY. In these cases, PLAN-B NET ZERO ENERGY will obtain the customer's consent to changes in another way.
23.5. If PLAN-B NET ZERO ENERGY makes use of the fiction of consent, the customer may terminate the contract affected by the change without notice and free of charge before the proposed effective date of the changes. PLAN-B NET ZERO ENERGY will specifically inform the customer of this right of termination in its change offer.
24.What happens in case of a dispute?
24.1. The place of jurisdiction is the customer's respective place of electricity consumption.
24.2. For questions and complaints regarding electricity supply, the customer, as a consumer according to §13 BGB, can contact PLAN-B NET ZERO ENERGY: PLAN-B NET ZERO ENERGY GmbH, Kurfürstendamm 188/189, 10707 Berlin.
24.3. For dispute resolution, private customers can apply for an arbitration procedure with Schlichtungsstelle Energie e.V. This requires that no mutually satisfactory solution has been found between the customer and PLAN-B NET ZERO ENERGY customer service. PLAN-B NET ZERO ENERGY is obliged to participate in the arbitration procedure. Schlichtungsstelle Energie e.V. Friedrichstraße 133 10117 Berlin Tel. 030-2757240-0, Fax 030-2757240-69 E-Mail: info@schlichtungsstelle-energie.de Internet: www.schlichtungsstelle-energie.de
24.4. The EU Commission has provided an internet platform for online dispute resolution (the "ODR platform"). The ODR platform serves as a point of contact for out-of-court settlement of disputes concerning contractual obligations arising from online sales contracts. The ODR platform can be accessed via the following link: https://ec.europa.eu/consumers/odr
25.Where can one get further information about the currently applicable tariffs?
25.1. The currently applicable tariffs and bundled products can be viewed on the website www.planbnetzero-energy.com.
25.2. Upon conclusion of the contract, the customer will receive a welcome email with all contract components and agreed prices.
25.3. The prices currently applicable to the ongoing contract can also be viewed by the customer in their customer account once they are being supplied.
26.How can customer service be reached?
Customers can reach customer service by email: kunde@planbnetzero-energy.com or via the customer portal.
27.How can the Consumer Service of the Federal Network Agency be reached?
The Consumer Service of the Federal Network Agency provides information on applicable law, the rights of household customers, and dispute resolution procedures for electricity and gas, and can be reached at the following contact details: Bundesnetzagentur für Elektrizität, Gas, Telekommunikation, Post, Eisenbahnen Verbraucherservice Postfach 8001 53105 Bonn Mon-Fri: 9 AM to 3 PM Tel. 030-22480-500 (nationwide information hotline) Fax 030-22480-323 E-Mail: verbraucherservice-energie@bnetza.de
28.Where can one get advice on energy matters?
Information on how to reduce energy consumption can be obtained from the Federal Office for Energy Efficiency (https://www.bfeeonline.de/BfEE/DE/Home/home_node.html), the German Energy Agency DENA (https://www.dena.de/startseite/), and the consumer centers (https://www.verbraucherzentrale.de/wissen/energie).
General Terms and Conditions
PLAN-B NET ZERO ENERGY GmbH
As of: 05/2026
§ 1 Scope of Application, Definitions
1) Scope of Application
These General Terms and Conditions ("GTC") govern the supply of electrical energy to household customers by PLAN-B NET ZERO ENERGY GmbH, Dieselstraße 2, 63165 Mühlheim am Main ("PBNZE", "we"), for the contractually agreed supply point, outside of basic and substitute supply, within the framework of a special customer contract.
A household customer is an end consumer who primarily purchases energy for self-consumption in the household ("Customer", "you").
The electricity supply contract is subject to the condition that:
- the customer's annual electricity consumption is below 50,000 kilowatt-hours (kWh) per billing year
- none of the following metering devices are used:
- Metering device with recording interval metering
- Dual-tariff meter with reduced grid fees
- Meter with a temperature-dependent load profile
- Customer's metering point in a foreign control area
2) Rate Plan
The rate plan applicable to the customer is determined by the offer presented during the ordering process.
3) Authorization
Upon conclusion of the contract, the customer authorizes PBNZE to register with the local grid operator and to terminate an existing contract for the specified supply point with the previous supplier. The customer will provide PBNZE with the necessary contract data for this purpose.
4) Smart Metering System
If the customer has given their consent to the ordering of a smart metering system (Section 2 No. 7 Metering Point Operation Act – "MsbG") at the time of contract conclusion or at a later date, PBNZE is entitled to request or initiate the early installation of a smart metering system at the metering point from the responsible metering point operator. The costs incurred for this will be passed on by PBNZE to the customer in corresponding application of Sections 4(5) and 5.
The costs are determined by the current version of the MsbG in conjunction with the price list of the responsible metering point operator. The costs applicable at the time of contract conclusion will be communicated to the customer on the PBNZE website and the PBNZE app, as well as in the contract confirmation. In the event of an order for a smart metering system after contract conclusion, the customer will receive a corresponding amendment confirmation ("Änderungsbestätigung").
5) Amendment of the General Terms and Conditions
PBNZE is entitled to amend these General Terms and Conditions if, after conclusion of the contract, unforeseeable changes occur that were not initiated by PBNZE and over which PBNZE has no influence, and if these changes significantly disturb the equivalence of performance and consideration.
Changes in this sense may be caused in particular by:
- new or amended legal bases
- new case law
- new or amended determinations or other decisions by the Federal Network Agency or other authorities
PBNZE will only amend the General Terms and Conditions if and to the extent that the amendment is necessary to restore the equivalence of performance and consideration or if regulatory gaps cause significant difficulties in contract execution.
PBNZE will notify the customer of the respective changes in text form at least one month before their planned effective date. The customer has the option to object to the changes in text form at the time of their planned effective date. Timely dispatch of the objection is sufficient to meet the deadline. If the customer does not object or does not object in due time, the changes are deemed approved.
In addition, the customer may terminate the contract in text form without notice at the time of the planned effective date. PBNZE will specifically inform the customer of the consequences of a failure to object and of the right to terminate the contract without notice when changes are announced.
Changes to the electricity price are made exclusively in accordance with Sections 4 and 5.
§ 2 Conclusion of Contract
1) Formation of the Contract
a) The presentation and promotion of PBNZE's services on the PBNZE website (www.planbnetzero-energy.com) and/or in the PBNZE app does not constitute a binding offer to enter into a contract, but is merely an invitation for the customer to submit an offer to PBNZE (so-called invitatio ad offerendum).
b) The customer can submit a binding offer to conclude an electricity supply contract by clicking the button with the text "Conclude contract with obligation to pay" on the PBNZE website and in the PBNZE app, providing all essential data. Until the offer is submitted, the customer can review their information in the online form at any time and, if necessary, correct it using the back buttons.
c) PBNZE will electronically confirm receipt of the offer and accept the customer's offer ("Acknowledgement of Receipt and Contract Confirmation"). The electricity supply contract is concluded upon receipt of the Acknowledgement of Receipt and Contract Confirmation. PBNZE will subsequently inform the customer of the start date of delivery in a separate communication. PBNZE allows the customer to pay for the supply of electricity and other services using insecure payment methods (invoice and SEPA direct debit). PBNZE therefore reserves the right to check the customer's creditworthiness before confirming the contract.
2) Ordering a smart metering system after contract conclusion
In the event of ordering a smart metering system after the conclusion of the electricity supply contract (see § 1(4)), the agreement on the amendment of the electricity supply contract ("Amendment Agreement") is concluded as follows:
a) The customer can declare their consent to order a smart metering system by clicking the checkbox on the PBNZE website and in the PBNZE app, and submit a binding offer to conclude the amendment agreement by clicking the button with the text "Conclude contract with obligation to pay". Until the offer is submitted, the customer can review their consent at any time and, if necessary, correct it by unchecking the box or cancel the ordering process.
b) PBNZE will electronically confirm receipt of the offer ("Acknowledgement of Receipt") with a copy of these General Terms and Conditions. The Acknowledgement of Receipt does not yet constitute acceptance of the offer by PBNZE. The amendment agreement is only concluded and the change to the electricity supply contract comes into effect upon receipt of the amendment confirmation.
3) Supplier Change
In the event of a supplier change, a prerequisite for the start of supply is that PBNZE receives confirmation from the previous supplier regarding the termination of the customer's previous electricity supply relationship.
4) Storage of Contract Text
The contract text (acknowledgement of receipt with the respective valid General Terms and Conditions and contract confirmation or amendment confirmation) will be stored by PBNZE after the contract is concluded and transmitted to the customer, but will no longer be accessible online to the customer.
5) Start of Supply
Delivery typically begins in accordance with the regulations for supplier changes, no later than three weeks after the grid usage registration is received by the grid operator responsible for the customer, but not before the termination of the previous electricity supply contract. The customer may also specify a preferred start date for delivery in their order. If the desired date is not feasible, delivery will commence on the earliest possible date.
6) Grid Operator Liability
In the context of supplier switching processes, the grid operator is not an auxiliary agent of PBNZE, and PBNZE is not liable for an incorrect registration confirmation by the grid operator.
7) Point of Delivery
PBNZE is obliged to provide electricity at the customer's electricity meter (point of delivery).
8) Power of Attorney for Representation
If a third party acts in the name or on behalf of the customer, PBNZE reserves the right to revoke the contract unless the customer sends a power of attorney to kunde@planbnetzero-energy.com upon request by PBNZE.
9) Contract Language
The contract language is German.
§ 3 Statutory Right of Withdrawal
1) Right of Withdrawal for Consumers
If the customer is a consumer (§ 13 BGB), they are entitled to a right of withdrawal in accordance with statutory provisions. The right of withdrawal applies to both the electricity supply contract and the amendment agreement, provided that the conditions specified below are met in each case. The consequences of withdrawal are limited to the electricity supply contract or the amendment agreement for which the customer exercises the right of withdrawal.
2) Instructions on Withdrawal
The right of withdrawal is subject to the regulations detailed in the following instructions on withdrawal:
Instructions on Withdrawal
You have the right to withdraw from this contract within fourteen days without giving any reason.
The withdrawal period is fourteen days from the day the contract is concluded.
To exercise your right of withdrawal, you must inform us (PLAN-B NET ZERO ENERGY GmbH, Dieselstraße 2, 63165 Mühlheim am Main, E-Mail: kunde@planbnetzero-energy.com) of your decision to withdraw from this contract by means of a clear statement (e.g., a letter sent by post or an email). You may use the attached sample withdrawal form, but this is not mandatory.
To meet the withdrawal deadline, it is sufficient for you to send your notification of exercising the right of withdrawal before the withdrawal period has expired.
Consequences of Withdrawal
If you withdraw from this contract, we must reimburse you for all payments we have received from you, including delivery costs (with the exception of additional costs resulting from your choice of a type of delivery other than the inexpensive standard delivery offered by us), without undue delay and at the latest within fourteen days from the day on which the notification of your withdrawal from this contract was received by us.
For this repayment, we will use the same means of payment that you used for the original transaction, unless expressly agreed otherwise with you; in no case will you be charged any fees for this repayment.
If you have requested that the services or electricity supply begin during the withdrawal period, you must pay us a reasonable amount corresponding to the proportion of services already rendered up to the point you inform us of your exercise of the right of withdrawal concerning this contract, compared to the total scope of services provided for in the contract.
Model Cancellation Form
(If you wish to revoke the contract, please fill out this form and send it back.)
- To PLAN-B NET ZERO ENERGY GmbH, Dieselstraße 2, 63165 Mühlheim am Main, E-Mail: kunde@planbnetzero-energy.com
- I/We hereby revoke () by me/us () concluded contract for the purchase of the following goods ()/the provision of the following service ()
- Ordered on ()/received on ()
- Name of the consumer(s)
- Address of the consumer(s)
- Signature of the consumer(s) (only when notified on paper)
- Date
(*) Delete as appropriate.
Section 4 Electricity Price
1) Payment Obligation
The customer is obliged to pay for the electrical energy consumed.
2) Price Components
The electricity price includes the following components:
- a) the spot market price (see 3))
- b) the other price components, including the PBNZE fee (see 6))
3) Spot Market Price
The spot market price (ct/kWh) corresponds to the spot market prices of EPEX Spot SE. EPEX Spot SE is the European exchange for short-term electricity trading. Among other things, EPEX Spot SE operates the Day-Ahead electricity market in Germany. There, once a day, prices for each hour of the following day are determined and published in EUR per MWh.
The determined prices can be viewed on:
- the website of EPEX Spot SE: https://www.epexspot.com/en/basics-powermarket
- the website www.planbnetzero-energy.com
- in the PBNZE app
The price determined in this way for each individual hour of the following day is passed on to the customer.
For clarification: The spot market price is adjusted automatically, and PBNZE has no discretion regarding changes to spot market prices.
Risk Notice: PBNZE expressly informs the customer that the prices applicable for each hour of a day are not fixed in advance but change hourly depending on spot market prices. This presents both opportunities and risks for the customer compared to an electricity supply contract with a fixed price.
Spot market prices can thus fall below the prices of fixed-price offers available on the market, which can lead to (significant) savings in electricity procurement costs for the customer. However, spot market prices can also exceed the fixed prices for electricity supply offered on the market. In the latter case, the customer has no protection against electricity costs that may significantly exceed the price level of comparable fixed-price contracts.
4) Hourly Billing
If the customer has a smart metering system according to § 2 No. 7 MsbG, a free metering system according to § 2 No. 13 MsbG, or any other technical device that enables hourly transmission of the customer's consumption (collectively referred to as "SmartMeter"), hourly allocation will be based on the actual energy consumption in the respective hour.
In the case of a smart metering system according to § 2 No. 7 MsbG, this only applies if the metering point operator PBNZE provides the hourly meter readings in an appropriate form. For a free metering system according to § 2 No. 13 MsbG or any other technical device, hourly allocation of consumption is only possible if the respective metering system or technical device is integrated into PBNZE's system. The metering systems and technical devices integrated into PBNZE's system are available on the website www.planbnetzero-energy.com.
If the customer's electricity consumption is measured with a conventional metering device or a modern metering device according to § 2 No. 15 MsbG without transmitting hourly values, or if hourly measurement of the customer's electricity consumption is not possible for other legal or factual reasons, the hourly spot market prices determined according to paragraph (3) will be assigned to the energy consumption based on the standard load profile applicable to the customer.
Should a permanent switch from hourly billing to billing based on the applicable standard load profile become necessary during the contract term for legal or factual reasons, PBNZE may make a corresponding switch to billing based on the applicable standard load profile. For the notification by PBNZE and the customer's right of termination, § 5(3) sentences 2 to 6 apply accordingly.
5) Smart Metering System for Hourly Billing
Insofar as there is a legal claim to the installation of a smart metering system within a legally defined period, PBNZE may demand that the customer agrees to PBNZE asserting this legal claim, provided that their consumption is billed hourly without a smart metering system (§ 2 No. 7 MsbG).
If the customer refuses consent or if the claim is not fulfilled by the responsible metering point operator within the statutory period, PBNZE may switch the billing of electricity consumption to the currently valid standard load profile. For the notification of the switch to billing according to the standard load profile by PBNZE and the customer's right of termination, § 5(3) sentences 2 to 6 apply accordingly.
As long as hourly recording of energy consumption is not possible, potential savings from billing spot market prices according to paragraph (3) cannot be fully realized or cannot be realized at all.
6) Other Price Components
In addition to the spot market prices mentioned in section (3), the electricity price includes PBNZE's additional procurement costs (e.g., for the procurement of guarantees of origin for the supply of electricity generated from renewable energy) as well as the PBNZE fee.
In addition, the other price components consist of:
- Grid usage fees
- Fee for metering point operation, including any additional services ordered (unless this is part of a separate contract between the customer and a metering point operator)
- Value-Added Tax
- Electricity Tax
- Concession Fee
- Levies pursuant to Sections 12, 2 No. 17 of the Energy Financing Act (EnFG, CHP Surcharge and Offshore Surcharge)
- Levy pursuant to Section 19 (2) of the Electricity Grid Charges Ordinance (StromNEV)
Section 5 Changes to Other Price Components
1) Price Adjustments
If the other price components change according to Section 4(6), the electricity price for the customer will be adjusted accordingly. Changes to the other price components by PBNZE are made by unilateral determination of performance in the exercise of equitable discretion. The price change is subject to an equity review pursuant to Section 315 (3) of the German Civil Code (BGB). The customer has the right to have the price change reviewed by a civil court.
When PBNZE unilaterally determines performance, only cost changes that are relevant for calculating the other price components shall be taken into account.
- In the event of an increase in the other price components, PBNZE is entitled to increase the electricity price and pass on the cost increase accordingly.
- In the event of a decrease in the other price components, PBNZE is obliged to reduce the electricity price and pass on the cost reduction accordingly.
If the changes have both cost-reducing and cost-increasing effects, PBNZE will carry out an offset, so that depending on the proportion of cost-reducing and cost-increasing price components, an electricity price increase or decrease, or possibly even an unchanged electricity price, may result.
2) Equal Treatment of Increases and Decreases
PBNZE must determine the scope and timing of a price change in such a way that both increases and decreases in the other price components are taken into account according to the same objective and temporal criteria. In particular, PBNZE is obliged not to allow a longer period between the review of cost development and the implementation of a price change for cost reductions than for cost increases.
3) Information and Right of Termination
PBNZE will inform the customer of the intended change to the other price components at least one month before it takes effect. In the event of a change, the customer may terminate the contract without notice at the time the change is scheduled to take effect. The termination must be in text form. PBNZE will specifically inform the customer of the right to terminate in the information letter regarding the price change. The right to ordinary termination pursuant to Section 8(3) remains unaffected.
4) New Taxes and Levies
Paragraphs 1) to 3) also apply insofar as new taxes, levies or other state-imposed surcharges or reliefs affecting the procurement, generation, storage, grid usage (transmission and distribution), metering point operation or consumption of electrical energy become effective in the future.
5) Value Added Tax
Notwithstanding paragraphs 1) to 3), changes in VAT according to the Value Added Tax Act will be passed on to the customer at the time the change becomes effective, without prior notice and without the possibility of extraordinary termination.
§ 6 Liability, Statutory Warranty Rights
1) Exclusion of Liability for Grid Disruptions
In the event of an interruption or irregularities in the electricity supply, PBNZE is exempt from its performance obligations insofar as these are consequences of a disruption to grid operation, including the grid connection, or a disruption to metering point operation. Sentence 1 does not apply if the interruption is due to unauthorized actions by PBNZE or if PBNZE is responsible for the interruptions or irregularities.
PBNZE is obligated to promptly provide the customer, upon request, with information regarding the facts related to damages caused by the grid operator or metering point operator, to the extent that these facts are known to PBNZE or can be reasonably clarified by PBNZE.
The competent party for any customer claims, according to the Low Voltage Connection Ordinance (NAV), is the responsible distribution grid operator to whose grid the customer is connected.
2) Claims against Grid Operators
In the event of an interruption or irregularities in the electricity supply as a result of a disruption to the grid connection, the customer may be entitled to claims against the grid operator, to whose grid the customer's supply point is connected, in accordance with statutory provisions. PBNZE will gladly provide the customer with the grid operator's contact information upon request, but is not obligated to provide further support in asserting such claims.
3) Limitation of Liability
Moreover, PBNZE's liability – irrespective of the legal grounds – is excluded if the damage is solely based on a slightly negligent breach of non-essential duties by PBNZE. Non-essential duties are those whose observance by PBNZE the customer cannot rely on.
Furthermore, the liability of PBNZE and its vicarious agents for slight negligence is limited to foreseeable and contract-typical damages.
Liability for personal injury, for assuming a guarantee, for fraudulently concealed defects, and liability under the Product Liability Act remains unaffected.
4) Warranty
Statutory warranty rights apply.
§ 7 Billing
1) Billing Period
Electricity consumption is billed monthly by PBNZE. If the customer does not have a SmartMeter or if hourly billing is permanently not possible for the reasons stated in § 4(4) or § 4(5), the hourly determined prices will be billed based on the consumption calculated from the previous year's values in conjunction with the applicable standard load profile until the first meter reading is taken.
If no previous year's values are available, consumption will be calculated based on the consumption behavior of a customer group typical for the customer. If the customer credibly demonstrates that their consumption is significantly lower, this must be appropriately taken into account in the assessment.
Furthermore, for customers without a SmartMeter or for customers for whom hourly billing is permanently not possible according to § 4(4) or § 4(5), a corrected invoice will be issued based on the meter reading transmitted by the metering point operator at least once a year. Upon customer request, the corrected invoice will be issued semi-annually, quarterly, or monthly.
Additionally, customers can report their consumption data to PBNZE via the PBNZE app. Provided these data are validated and confirmed by the metering point operator, they will be included in the billing.
2) Delivery of Invoices
Billing is carried out electronically. Upon customer request, invoices and billing information will be provided in paper form once a year free of charge.
If consumption data is not transmitted remotely, the customer receives billing data every six months, or every three months upon request. If consumption data is transmitted remotely, the customer receives consumption information monthly.
3) Final Billing
The final billing is based on the respective meter readings at the supply point at the end of each billing period as defined in paragraph (1). If the billing results in a credit balance for the customer, PBNZE must pay this out within two weeks.
4) Final Billing upon Contract Termination
Upon termination of the electricity supply contract, any credit balance resulting from a corrected invoice will be refunded immediately. Invoicing will take place no later than three weeks after the end of the billing period or after the termination of the supply relationship. Any credit balance must be paid out within two weeks.
5) Due Date
Invoices are due on the specified payment date, but no earlier than fourteen calendar days after receipt of the invoice.
6) SEPA Direct Debit Procedure
Invoice payments are made via SEPA direct debit. The customer grants PBNZE a corresponding direct debit mandate. PBNZE must inform the customer of the direct debit amount at least one day before execution. The customer is responsible for ensuring that their account has sufficient funds to meet their payment obligations under this contract. The customer must reimburse PBNZE for any costs incurred due to a chargeback for which the customer is responsible.
7) Bank Transfer
Instead of the SEPA direct debit procedure, the customer may choose to pay invoices by bank transfer. Transfers must be made to the account specified by PBNZE. The decisive factor for timely payment is the value date on PBNZE's account.
Section 8 Contract Term and Termination
1) Minimum Term
There is no minimum term for the contract.
2) Contract Duration
The contract runs for an indefinite period.
3) Ordinary Termination
The electricity supply contract can be terminated by either party in text form with four weeks' notice. Section 5(3) remains unaffected. PBNZE will confirm any customer termination, regardless of the legal reason, in text form within one week of receipt, stating the contract end date.
4) Termination upon Relocation
In the event of a relocation, the customer may terminate the contract with six weeks' notice, effective either upon moving out or at a later date, unless PBNZE offers the customer, within two weeks of receiving the termination notice in text form, a continuation of the supply contract at the new residence under the existing contract terms and supply is possible at the new consumption point.
The customer must notify PBNZE of the relocation in text form one month prior to the move, stating the new address and the specific move-out and move-in dates.
If PBNZE is unable to supply the new delivery point, it will inform the customer in text form. If the customer is unable to receive electricity at the new delivery point, they will inform PBNZE in text form.
5) No Termination Fees
PBNZE may not charge separate fees for contract termination, especially due to a supplier change.
§ 9 Extraordinary Termination
The contract may be terminated by either party for good cause without notice, in text form.
PBNZE is entitled to extraordinary termination, particularly if the customer repeatedly fails to meet payment obligations despite reminders, or fails to meet a payment obligation despite repeated reminders, and if the extraordinary termination was threatened at least two weeks in advance.
This does not apply if the consequences of the extraordinary termination are disproportionate to the severity of the breach or if the customer demonstrates to PBNZE's satisfaction that there is a sufficient prospect of them fulfilling their payment obligations.
§ 10 Data Protection
PBNZE processes the customer's personal data, including its collection, storage, and use, in accordance with legal regulations and the privacy policy available here.
§ 11 GHG Quota
Under the Greenhouse Gas Reduction Quota, or GHG quota for short, PBNZE customers who operate a charging station and own a registered electric vehicle can sell their GHG quota potential, linked to electric charging current, to companies subject to quota obligations via a third-party GHG service provider.
The details regarding the selection of the third GHG service provider are set out in the General Terms and Conditions of the GHG service provider cooperating with PBNZE. By registering with PBNZE for the GHG quota, personal data (name, email address) will be transmitted to the GHG service provider responsible for processing the quota sale.
§ 12 Statutory Information Obligations
1) Contact and Complaints
Customers can address questions regarding contracts, invoices, or electricity supply, or complaints, particularly concerning contract conclusion or the quality of PBNZE's services, to PBNZE via the PBNZE app, PBNZE's website, or by email (kunde@planbnetzero-energy.com) or post (PLAN-B NET ZERO ENERGY GmbH, Dieselstraße 2, 63165 Mühlheim am Main). PBNZE is obliged to respond to a complaint within four weeks of receipt.
2) Arbitration Procedure
To resolve disputes, the customer can apply for an arbitration procedure with the Energy Arbitration Board e.V.:
Energy Arbitration Board e.V.
Friedrichstraße 133
10117 Berlin
Phone: 030 2757240-0
Fax: 030 2757240-69
Email: info@schlichtungsstelle-energie.de
Website: www.schlichtungsstelle-energie.de
Such an application is only admissible if PBNZE has not remedied the consumer complaint within four weeks of receipt at the latest. PBNZE is obliged to participate in the arbitration procedure.
The right of the parties to appeal to the courts or to request another procedure under the EnWG remains unaffected. Submitting a complaint to the arbitration board suspends the statutory limitation period in accordance with Section 204 (1) No. 4 of the German Civil Code (BGB).
3) Online Dispute Resolution
The European Commission provides a platform for online dispute resolution (ODR) (available at: http://ec.europa.eu/consumers/odr/). PBNZE is neither obliged nor willing to participate in this dispute resolution procedure.
4) Energy Consumer Service
General information on consumer rights is available from the Federal Network Agency's Energy Consumer Service:
Energy Consumer Service
Federal Network Agency
P.O. Box 8001
53105 Bonn
Phone: 030 22480-500
Fax: 030 22480-323
Email: verbraucherservice-energie@bnetza.de
PLAN-B NET ZERO ENERGY GmbH
Dieselstraße 2
63165 Mühlheim am Main
As of: October 2023